Medway Action Plan

To achieve our shared Vision for the Medway, the Partnership have created a Catchment Plan which you can explore below. This plan outlines the Aims, Objectives and Actions required to achieve our shared Vision, restoring the River Medway and all its tributaries back to health. 

Our Aims:

  1. The river should support a mosaic of habitats with high biodiversity value
  2. To have an appropriate self-sustaining fish population
  3. To restore the river to a more naturally functioning watercourse
  4. To improve water quality
  5. To develop sustainable water management within the catchment
  6. To have communities that enjoy, engage with and protect the river

Explore the map and table below to find out more. 

Displaying 1 - 16 of 16
To have an appropriate self-sustaining fish population
Address fish passage so fish can access appropriate habitats
Action Sub catchment Partners Status Activities
Creation of fish passage at Dairyhouse Weir Teise Completed 0 View
Develop fish passage projects within the Teise Teise Active 0 View
Create fish passage at Gatehouse weir Teise Completed 0 View
Create fish passage at New Lodge Weir Teise Completed 0 View
Action Sub catchment Partners Status Activities
Improve fish passage at Harpers Weir by removal of redundant structure Teise Completed 0 View
Habitat enhancement on the River Teise below Woodfall's weir to Medway confluence Teise 0 View
To restore the river to a more naturally functioning watercourse
Enhance river hydromorphology and biodiversity
Action Sub catchment Partners Status Activities
Add woody debris and berm deflector to increase flow diversity at Bayham L'Eglise. Teise Completed 0 View
Restore habitat at Harpers Weir Teise Completed 0 View
Adjustment to flow regimes from Bewl water Teise 0 View
Habitat restoration on the River Bewl Teise Completed 0 View
Investigate options to address negative impacts of Duddies Sluice. Teise Proposed 0 View
Investigate options to address negative impacts of Darman's Sluice. Teise Proposed 0 View
Assess options for habitat improvement at Crowbourne Backwater. Teise Proposed 0 View
Address over abstraction
Action Sub catchment Partners Status Activities
Aim to create on-farm reservoir at Pikefish Farm to improve water sustainability and reduce summer abstraction from the river. Teise Proposed 0 View
To develop sustainable water management within the catchment
Reduce the impact of flooding
Action Sub catchment Partners Status Activities
Natural flood management at Bedgebury Pinetum to reduce flood risk downstream and offer additional benefits. Teise Completed 0 View
The river should support a mosaic of habitats with high biodiversity value
Improve condition and biodiversity of riparian areas
Action Sub catchment Partners Status Activities
Work up designs, secure permissions and deliver habitat improvement works Teise Active 0 View

Catchment wide actions